1. Define the task and the view
On the elevation, mark the surface to be lit and the normal viewing positions. A display, preparation counter and decorative recess have different purposes. Mark likely obstructions such as rails, shelf contents, doors and appliances.
The output is a labelled application drawing—not simply a photograph captioned “warm lighting”.
2. Approve the section before machining
Show the complete profile, cover, end cap, connector and cable exit within the permitted furniture machining zone. Check structural constraints with the furniture designer. Include removal access for the cover and connections.
The output is one cross-section with component references and a revision.
3. Create the section schedule
Record usable length, end allowances, the selected strip's permitted cut interval, finished section length and quantity. For example, an opening dimension and a finished strip dimension can differ; do not copy the furniture width into every order field.
The output is a cut schedule tied to the drawing.
4. Map the electrical and operating zones
Total confirmed loads by branch and by supply/control group. Mark cable paths, connection points and service locations. Describe the required switch, sensor, dimming or adjustable-white behaviour. Have the responsible professional review equipment compatibility and installation requirements.
The output is a zone diagram and a named equipment list, not an unreviewed generic wiring picture.
5. Release a reproducible assembly
Review a representative mounted assembly against the intended task, view and operating scene. Record mechanical fit, useful light, source appearance, colour and controls separately. Keep required test or compliance evidence distinct from visual approval.
| Deliverable | Owner to identify |
|---|---|
| Furniture elevation and structural/machining constraints | Furniture designer |
| Exact strip and accessory references | Supplier and buyer |
| Reviewed electrical arrangement | Responsible installer/designer |
| Accepted sample and required evidence | Authorised project approver |
| Frozen BOM and drawing revision | Buyer/production team |
If a shelf dimension changes, recheck the connected decisions. A revised length can affect cut units, accessory positions and loads. The guide's purpose is coordination; the individual technical articles contain the detailed calculations and comparisons.